SPPROHRW key milestones (2024 - 2025)
May 17, 2024
- The SPPROHRW project proposal submitted following the Pandemic Fund Second Call for Proposals
Sep 19, 2024
- The Pandemic Fund allocated $128.89 million to boost Mpox response in 10 countries, including $24.9 million for Rwanda’s SPPROHRW
Oct 07, 2024
- A post-approval change request submitted to the Pandemic Fund to align the proposal with national and continental Mpox response plans.
Nov 15, 2024
- Official start of project implementation
Feb 15, 2025
- Midterm report submitted
Feb 26, 2025
- A high-level meeting convened to review project progress
- The project proposal reviewed to ensure efficiency and long-term impact
May 09, 2025
- A second post-approval project request submitted to the Pandemic Fund following the project review
May 15, 2025
- Six months report submitted
May 15-16, 2025
- A delegation from the Pandemic Fund Secretariat conducted a site visit to Rwanda
Jun, 2025
- Project implementation commences pending formal approval of the change request
July 2, 2025
- The second post-approval change request submitted to the Pandemic Fund was approved, following its classification as a “minor” change.
Jul 01-31, 2025
Annual report submission